Implementation of Nitish Kumar's dream project under question mark


Patna, Jan 5 (IANS): While Bihar Chief Minister Nitish Kumar was busy in taking a high-level meeting at the secretariat in Patna, one of his dream projects -- water connectivity to every house called "Har Ghar Nal Ka Jal" Program -- appeared not properly being implemented on ground at several places in the state.

A newly constructed overhead water tank built under "Saat Nishchay" scheme was collapsed within five minutes as a submersible pump was started to fill water in it in Beldhar Bigha village of Gaya district.

The incident has created chaos in the area. Fortunately, no one came under the debris of the tank. The villagers alleged that the contractor had used low-quality material in the construction of this tank.

This was not the first case, similar incidents have also been reported in Khagaria, Nalanda and Nawada districts as well.

This scheme is having a scope of scam and it is appearing from time to time in Bihar. Darbhanga police have also arrested a Ward Secretary and Ward Member in connection with the alleged embezzlement of the government funds.

Darbhanga police have arrested Ward Secretary Vijay Yadav of Benipur Block for embezzling Rs 2,29,000 on Monday while Ward Member Shatrudhan Mukhiya was arrested for taking away Rs 13,48,400.

Anmol Mishra, Block Development Officer of Benipur in Darbhanga, had registered a complaint on November 26 after the detection of fraud. He said that the arrest was made after proper investigation by the police.

The Chief Minister on Monday held a high-level meeting to analyze development projects in Bihar.

He took a review of "Har Ghar Nal Ka Jal" scheme. Besides, he also approved easy road connectivity to every village. As per the plan, he has given direction to the Road Construction Department to connect every village with important places.

An Additional Chief Secretary level officer of the Road Construction Department presented a plan to construct 120 bypass roads in important cities, sub towns and blocks across the state.

According to the plan, the total length of these roads is estimated to be 708 km. These will be constructed at an estimated cost of Rs 4,154 crore in 48 months. 31 bypasses will be constructed alongside national highways and the remaining 89 are on state highways.

  

Top Stories


Leave a Comment

Title: Implementation of Nitish Kumar's dream project under question mark



You have 2000 characters left.

Disclaimer:

Please write your correct name and email address. Kindly do not post any personal, abusive, defamatory, infringing, obscene, indecent, discriminatory or unlawful or similar comments. Daijiworld.com will not be responsible for any defamatory message posted under this article.

Please note that sending false messages to insult, defame, intimidate, mislead or deceive people or to intentionally cause public disorder is punishable under law. It is obligatory on Daijiworld to provide the IP address and other details of senders of such comments, to the authority concerned upon request.

Hence, sending offensive comments using daijiworld will be purely at your own risk, and in no way will Daijiworld.com be held responsible.