Avalanche affects operations at JP Power's Vishnuprayag project


New Delhi, Feb 8 (IANS): The massive avalanche in Chamoli, Uttarakhand has led to the closure of power generation at Jaiprakash Power Venture Ltd 400 MW Vishnuprayag Hydro Electric Project.

In a regulatory filing, Jaiprakash Power said it is confident that the project will resume operations in a few days after the completion of the cleaning process and the checking of all aspects.

The project's barrage is over Alaknanda River, and its Tail Race Tunnel discharging water is in the river Dhauli Ganga. River water gushed in through the Tail Race Tunnel of the project bringing with it the slush, the filing said.

"We are analysing all aspects and assessing the time to bring back the project to its pre closure status (operations were stopped at 11 a.m. on 7th Feb due to this tragic Glacier event)," it said.

Jaiprakash Power also said that it is providing full assistance and assurance to the district authorities since Sunday in the relief operations and will continue to provide all humanitarian aid.

  

Top Stories


Leave a Comment

Title: Avalanche affects operations at JP Power's Vishnuprayag project



You have 2000 characters left.

Disclaimer:

Please write your correct name and email address. Kindly do not post any personal, abusive, defamatory, infringing, obscene, indecent, discriminatory or unlawful or similar comments. Daijiworld.com will not be responsible for any defamatory message posted under this article.

Please note that sending false messages to insult, defame, intimidate, mislead or deceive people or to intentionally cause public disorder is punishable under law. It is obligatory on Daijiworld to provide the IP address and other details of senders of such comments, to the authority concerned upon request.

Hence, sending offensive comments using daijiworld will be purely at your own risk, and in no way will Daijiworld.com be held responsible.