Daijiworld Media Network - Panaji
Panaji, Nov 26: The Goa government has notified amendments to the Goa Land Development and Building Construction Regulations, 2026, allowing additional Floor Area Ratio (FAR) and building height for eligible developments across the State.
The government informed the High Court of Bombay at Goa on Wednesday that the amendments were published in the Extraordinary Official Gazette by the Department of Town and Country Planning on November 24 and came into force immediately.

Under the newly introduced Regulation 6.1.2, the government may grant additional FAR and building height on the recommendation of the TCP Board for developments in municipal, planning and village areas, provided the plot measures at least 300 square metres.
Annexure XIII-A links the additional FAR and height to the existing permissible FAR and the width of the road adjoining the plot, ranging from six metres to 10 metres and above. The maximum total FAR has been capped at 300, calculated on the total net effective plot area, while the building height cannot exceed 40 metres. A stricter height limit of 14.9 metres applies to certain lower-FAR zones along roads measuring six to 10 metres wide.
The concessions apply to residential and settlement, commercial, public and semi-public, institutional, transport, warehousing, communication and industrial zones. However, Goa Industrial Development Corporation estates and industrial areas have been excluded.
Four- and five-star hotel projects are not eligible for the concessions. Projects on plots measuring 500 square metres or more along roads at least eight metres wide must submit a notarised affidavit undertaking that the additional FAR or height will not be used to establish such hotels.
Developments within protected monument buffer zones are also excluded, while coastal regulation zone areas will continue to be governed by applicable coastal regulations.
Developers must pay the prescribed fees before obtaining technical clearance and comply with setback, structural safety, existing building load-bearing capacity and additional parking requirements. A No Objection Certificate from the Fire and Emergency Services Department is mandatory before applying for a construction licence.
The amendments also make rainwater harvesting compulsory for all projects. Solar photovoltaic systems and/or solar water heating facilities must cover at least five per cent of the sanctioned load.
Projects consuming more than 9.7 kilolitres of water per day in areas without sewerage facilities must install sewage treatment plants (STPs). However, the government may relax this requirement for proposals approved earlier.
The High Court has scheduled the matter for January 19.