Work advances at Rio 2016 venues


Rio de Janeiro, Oct 17 (IANS) The construction work at three Rio 2016 venues is in progress as the city steps up its Olympic preparations, local organizers have said.

The structures for spectator stands have already been built at indoor arenas earmarked for basketball, judo, fencing, taekwondo, wheelchair basketball, wheelchair rugby, boccia and judo, Xinhua cited from the Rio 2016 website.

The work on the adjacent Olympic tennis centre, which will seat 10,000 people, is also "taking shape", organizers said.

"Significant progress has been made and we are happy to see that work is proceeding as planned, and in some cases, is ahead of schedule," said Rio 2016 infrastructure integration director Alexandre Techima.

Meanwhile, foundations are being laid for the Olympic Velodrome and Aquatics Stadium.

Rio Olympic Arena and Maria Lenk Aquatics Centre are scheduled to undergo refurbishment work in the first quarter of 2015.

  

Top Stories


Leave a Comment

Title: Work advances at Rio 2016 venues



You have 2000 characters left.

Disclaimer:

Please write your correct name and email address. Kindly do not post any personal, abusive, defamatory, infringing, obscene, indecent, discriminatory or unlawful or similar comments. Daijiworld.com will not be responsible for any defamatory message posted under this article.

Please note that sending false messages to insult, defame, intimidate, mislead or deceive people or to intentionally cause public disorder is punishable under law. It is obligatory on Daijiworld to provide the IP address and other details of senders of such comments, to the authority concerned upon request.

Hence, sending offensive comments using daijiworld will be purely at your own risk, and in no way will Daijiworld.com be held responsible.