Goa's new airport to be commissioned by August 2022


Panaji, Jul 29 (IANS): The first phase of Goa's upcoming Mopa international airport will be commissioned by August 2022, Chief Minister Pramod Sawant told the state Legislative Assembly during the ongoing Monsoon Session.

Sawant also said that 34.24 per cent of the airport project work has been completed by June 2021.

"The development of greenfield international airport at Mopa in Pernem taluka is in progress and the first phase is expected to be commissioned by August 2022," Sawant said in a written reply to a question from BJP MLA Nilkanth Halarnkar.

"The physical progress achieved till June 30 2021 is 34.24 per cent," Sawant also said.

To another question by another BJP MLA Atanasio Monserrate, Sawant in his written reply said that the airport project has faced a time and cost escalation due to "restraint by courts and pandemic".

"The initial estimated cost of the project is Rs 1,900 core and the same is revised to Rs 2,615 crore," Sawant said.

 

  

Top Stories


Leave a Comment

Title: Goa's new airport to be commissioned by August 2022



You have 2000 characters left.

Disclaimer:

Please write your correct name and email address. Kindly do not post any personal, abusive, defamatory, infringing, obscene, indecent, discriminatory or unlawful or similar comments. Daijiworld.com will not be responsible for any defamatory message posted under this article.

Please note that sending false messages to insult, defame, intimidate, mislead or deceive people or to intentionally cause public disorder is punishable under law. It is obligatory on Daijiworld to provide the IP address and other details of senders of such comments, to the authority concerned upon request.

Hence, sending offensive comments using daijiworld will be purely at your own risk, and in no way will Daijiworld.com be held responsible.