Lobo apologises for Calangute infrastructure work delays, promises December completion


Daijiworld Media Network - Calangute

Calangute, Nov 28: Calangute MLA and Goa State Infrastructure Development Corporation (GSIDC) chairperson Michael Lobo has apologised to residents for the inconvenience caused by delays in major infrastructure works in his constituency, following repeated criticism over the slow pace of the project.

“I’m sorry for your troubles in the last few months over the delayed work,” Lobo said, acknowledging the difficulties faced by residents and motorists.

The infrastructure works, which began in June, were initially scheduled for completion by the end of November. The project, being executed through GSIDC, includes underground ducting for electricity and internet cables, upgrading of water pipelines and improvements to the drainage network.

Providing an update on the progress, Lobo said the ducting work had been completed and slab work was currently underway. Kerb stones are expected to arrive shortly, while tiles for the pavement have already been ordered.

However, underground cabling remains pending, with around 50 per cent of the cable crossings completed so far.

Lobo said road-levelling work would begin by the end of November, while hot-mixing of roads is expected to commence around December 10.

The first phase of the project stretches from the Calangute panchayat office to the Bandodkar statue. Lobo said the stretch up to the market junction is expected to be ready by mid-December, while the remaining portion is targeted for completion by mid-January.

He also announced plans to construct uniform-height pavements with red, yellow and black tiles, extending from the road edge to the shops. The initiative aims to eliminate uneven footpath levels and prevent accidents.

Lobo further said a similar footpath would be developed along the Baga road before the completion of his current term and the next Assembly elections.

  

Top Stories


Leave a Comment

Title: Lobo apologises for Calangute infrastructure work delays, promises December completion



You have 2000 characters left.

Disclaimer:

Please write your correct name and email address. Kindly do not post any personal, abusive, defamatory, infringing, obscene, indecent, discriminatory or unlawful or similar comments. Daijiworld.com will not be responsible for any defamatory message posted under this article.

Please note that sending false messages to insult, defame, intimidate, mislead or deceive people or to intentionally cause public disorder is punishable under law. It is obligatory on Daijiworld to provide the IP address and other details of senders of such comments, to the authority concerned upon request.

Hence, sending offensive comments using daijiworld will be purely at your own risk, and in no way will Daijiworld.com be held responsible.