Cabinet approves Rs 1.86 lakh crore Green Energy Corridor Phase-III


Daijiworld Media Network - New Delhi

New Delhi, Sep 30: The Union Cabinet on Wednesday approved the Green Energy Corridor Phase-III (GEC-III) scheme to facilitate the evacuation of up to 135 GW of renewable energy across states and Union Territories.

The scheme is targeted for completion by FY 2032-33 and has a total project outlay of Rs 1,86,405 crore. Of this, Rs 1,36,378 crore will be allocated for developing Intra-State Transmission Systems (InSTS) under GEC-III, while Rs 50,000 crore will be utilised for 50 GWh of Battery Energy Storage Systems (BESS).

According to an official statement, the scheme will support the deployment of 50 GWh of BESS at renewable energy developer or generator sites, or other locations important for grid flexibility.

The storage systems are aimed at addressing intermittency, transmission congestion and peak-hour curtailment, while helping meet electricity demand during non-solar hours.

The scheme will facilitate grid integration and power evacuation within states and Union Territories.

The government will provide total Central financial assistance of Rs 54,082 crore under the scheme.

The Central Financial Assistance (CFA) will help offset intra-state transmission charges and thereby keep electricity costs lower. The government support is expected to ultimately benefit end users.

The BESS component is also expected to boost manufacturing and deployment in the domestic energy storage industry and generate employment. The scheme will create long-term skilled jobs in operations, maintenance and grid management across participating states.

All greenfield projects under the InSTS component will be implemented through the Tariff Based Competitive Bidding (TBCB) mode, while brownfield upgrades and network-strengthening works will be carried out on a Cost Plus Basis (CPB).

State Transmission Utilities will serve as the overall implementing agencies, while Transmission Service Providers will participate in TBCB projects under the Build-Own-Operate-Maintain (BOOM) model.

The scheme is expected to contribute to the government's target of achieving 900 GW of installed non-fossil fuel capacity by 2035.

It will also support the country's long-term energy security and promote ecologically sustainable growth by reducing the carbon footprint.

The government said the initiative would generate direct and indirect employment across the power, manufacturing and construction sectors.

  

Top Stories


Leave a Comment

Title: Cabinet approves Rs 1.86 lakh crore Green Energy Corridor Phase-III



You have 2000 characters left.

Disclaimer:

Please write your correct name and email address. Kindly do not post any personal, abusive, defamatory, infringing, obscene, indecent, discriminatory or unlawful or similar comments. Daijiworld.com will not be responsible for any defamatory message posted under this article.

Please note that sending false messages to insult, defame, intimidate, mislead or deceive people or to intentionally cause public disorder is punishable under law. It is obligatory on Daijiworld to provide the IP address and other details of senders of such comments, to the authority concerned upon request.

Hence, sending offensive comments using daijiworld will be purely at your own risk, and in no way will Daijiworld.com be held responsible.