Mangalore : National Highway Phase 3 Makes Super Fast Progress
by Special Correspondent
Pics by Dayananda Kukkaje
Daijiworld Media Network - Mangalore
Mangalore, Feb 27 : For Mangaloreans who are fed up with the slow pace of the work of the Port Connectivity Project  taken   up almost five years ago on NH 17, NH 13 and NH 48, there is some good news.  The four-laning work on Kundapur-Surathkal and Nanthur –Talapady stretch , a total  about  90 kms,  is going on in full swing  and the work will be completed by March 2013. This project comes under phase 3 of National Highway Development Project  (NHDP) and the work on this entire stretch  involves  2 flyovers in Pumpwell  (Mahaveer Circle) and Thokkottu junction, two vehicular underpasses (VUP), one over pass, 10 cattle underpasses, 9 pedestrian underpasses (PUP), 9 major bridges ( including the Netravati bridge)   and equal number of minor bridges, one railway over bridge at Ekkur, 5 truck lay byes, 50 bus bays and bus shelters and 3 toll plazas and two bypasses, at Mulki and Padubidri.   40 kms of service road within the city limits is  also covered under this project. 
Except the  Pangala bridge,  8 other existing bridges will be set right and  parallel bridges will be constructed as part of four-laning work.  The existing Pangala bridge which has faulty alignment,  will be completely abandoned and a  6-lane new bridge will be constructed  instead.  The land acquisition process for the project is going on and  final notification is under completion.  NHAI is facing 5 litigations at the moment,  in this stretch of the project.  One litigation case pertaining to Nanthoor  bypass  is in the Supreme Court and   judgment  is expected within a week,   says Project Director  Prashanth N Gawasane.













The project has acquired environmental  and CRZ clearance and work has been going on from September 2010.   
According to Project Engineer Srinivas Rao,  work is going on simultaneously on 75 kms stretch on Kundapur-Surathkal and 17 kms stretch on Nanthoor-Talapadi.  “Work is going on day and night as we have  to complete  the project within the stipulated time. While construction activity is done mostly during  the day  dumping and mechanic work  is carried out  during  night.  We have about 250 workers including 50 odd engineers and supervisors at work.  The entire project  is carried out according to the specifications of NHAI  under whose supervision we are carrying out the work”,  Srinivas Rao  pointed out. 
Among the 9 bridges covered under the project, Netravathi  bridge with the length of 804 metres is the longest one and work of this  bridge including the minor bridge is going on in full swing.  “Work of about 75 pillars out of the 120 pillars of Natravathi  is completed and work on the remaining pillars is under progress.  New gantry barge which will help in the erection of pre-casting of beams will be built within a few days.  The contractors want to complete the building of pillars before the onset of monsoons”, said K M Hegde, Manager, Technical, NHAI.  “The company has set up 3 wet mix macadam plants, 2 concrete botching plants and 2 hot-mix plants  to speed up the work.  So far  our progress is 13 percent and this is as per schedule,  ”, Gawasane asserts. 
The entire project undertaken at a cost of about Rs. 670 crores is contracted to Hyderabad based  Navayug Udupi Tollway Private Limited, a   consortium of Navayug and  Krishnapattna Port Company Limited, set up  under the  special purpose vehicle (SPV) project.   Out of this Rs. 221.43 crores is borne by NHAI to make the project viable.  The project is based on the concept of build-operate-transfer (BOT) and as per the  agreement the  project is to be completed  within 910 days.    The company is given a concession of 25 years  that includes 910 days of construction period also.   This BOT  also known as public private  partnership (PPP)  is beneficial to the government because it does not have to invest in the project as the company will be investing  after availing bank loans and they will plough back the investment in the form of toll which they are entitled to collect for the next 25 years.  It also ensures that the company will maintain the road for this period.  
Though the project is contracted to Navayug Udupi Tollway Private Limited, NHAI is responsible for its implementation.   It has to acquire land, defend litigations,  ensure shifting of utilities including electricity, water supply, drainage etc,.  which is a time consuming and tedious process.  NHAI has appointed  independent consultants,  Aarvee Associates to supervise the project work.  
About 18,000 trees have been  cut to implement NHDP phase 3 project, which is no doubt a  huge loss  and rightly so the forest department has raised a hue and cry.  While Gawasane says that implementing   any enormous project involves  cutting of  trees, which cannot be totally avoided,  NHAI has  paid Rs 1.96 crores to the forest department for afforestation  purposes.  NHAI also has plans to help the cause of environment by planting medium size saplings and trees.  NHAI has also paid Rs  1.3 crores supervision charges to MESCOM for shifting the cables.  
Gawasane points out that with the help  and cooperation of people developmental work such as NHDP can be completed on a war footing.  But litigation and other compulsions such as shifting of utilities takes long time.  “We want full cooperation of the people so that we can complete the project well within the specified time.  People should understand that development is for their benefit.  Litigation issue  and the issue involving  shifting of  cables had resulted in cancelling the Nanthoor flyover.  It is a big loss to the people  of Mangalore and they should realize it”, Gawasane declared.    
Navayug Udupi Tollway Private Limited, which has been carrying out many prestigious projects in Bangalore and other  places,   possesses structural  expertise to accomplish the task assigned to it.   Going by the progress achieved in the last six months,  this project is sure to be completed well in time, much to the consternation  of many Mangaloreans.  
The nine bridges that come under the project  are:  
Mabukala -            290 metres
Bhadragiri               87 metres
Kallyanpura     203 metres
Udyavara               261 metres
Pangala     116 metres
Mulki      174 metres
Pavanje     145 metres
Nethravathi           804 metres
Talapadi                   70 metres