Delhi Metro to start Phase III trial runs by Dec 30


New Delhi, Dec 10 (IANS): The Delhi Metro said Tuesday it would start trial runs on the first section of the Phase III route between the Central Secretariat and Mandi House by Dec 30.

The trial runs will be done for opening the section to the public by March 2014, six months ahead of the earlier October 2014 date.

The construction on this stretch started Dec 2011.

"The opening of this stretch has been advanced by about six months as it will help in decongesting the Rajiv Chowk Metro station. This line will enable commuters on the Badarpur-Central Secretariat line, bound for Noida and Vaishali, to change trains at Mandi House without having to change twice at Central Secretariat and then at Rajiv Chowk," an official statement said.

The Mandi House station will be the first interchange station of the Phase III.

"The commissioning of this section before the scheduled date will benefit the public in a major way and ease pressure on Rajiv Chowk," DMRC managing director Mangu Singh said.

Phase III will provide interchange facility at the Central Secretariat and the Mandi House stations.

 

  

Top Stories


Leave a Comment

Title: Delhi Metro to start Phase III trial runs by Dec 30



You have 2000 characters left.

Disclaimer:

Please write your correct name and email address. Kindly do not post any personal, abusive, defamatory, infringing, obscene, indecent, discriminatory or unlawful or similar comments. Daijiworld.com will not be responsible for any defamatory message posted under this article.

Please note that sending false messages to insult, defame, intimidate, mislead or deceive people or to intentionally cause public disorder is punishable under law. It is obligatory on Daijiworld to provide the IP address and other details of senders of such comments, to the authority concerned upon request.

Hence, sending offensive comments using daijiworld will be purely at your own risk, and in no way will Daijiworld.com be held responsible.